Please see below the 3 lead time options:
Layer |
Quantity |
Dimension ( m2 per piece) |
Super Urgent |
Urgent |
Normal |
Single/Double |
1~20 Pieces |
1~2,000 cm2 |
3 Day |
4 Days |
5 Days |
|
21~55 Pieces |
1~225 cm2 |
3 Day |
3 Days |
5 Days |
|
|
225.01~1,225 cm2 |
4 Days |
5 Days |
6 Days |
|
|
1,225.01~2,000 cm2 |
5 Days |
6 Days |
7 Days |
|
56~100 Pieces |
1~225 cm2 |
4 Days |
5 Days |
6 Days |
|
|
225.01~1,225 cm2 |
5 Days |
6 Days |
7 Days |
|
|
1,225.01~2,000 cm2 |
6 Days |
7 Days |
8 Days |
|
101~200 Pieces |
1~225 cm2 |
5 Days |
6 Days |
7 Days |
|
|
225.01~1,225 cm2 |
6 Days |
7 Days |
8 Days |
|
|
1,225.01~2,000 cm2 |
7 Days |
8 Days |
9 Days |
4 Layer |
1~20 Pieces |
1~2,000cm2 |
3 Day |
4 Days |
6 Days |
|
21~55 Pieces |
1~2,000 cm2 |
4 Days |
5 Days |
7 Days |
|
56~100 Pieces |
1~2,000 cm2 |
6 Days |
7 Days |
9 Days |
|
101~200 Pieces |
1~2,000 cm2 |
7 Days |
8 Days |
10 Days |
6 Layer |
1~10 Pieces |
1~2,000 cm2 |
3 Day |
6 Days |
8 Days |
|
11~20 Pieces |
1~2,000 cm2 |
4 Days |
7 Days |
9 Days |
|
21~50 Pieces |
1~2,000 cm2 |
5 Days |
8 Days |
10 Days |
8 Layer |
1~10 Pieces |
1~2,000 cm2 |
4 Days |
7 Days |
10 Days |
|
11~20 Pieces |
1~2,000 cm2 |
5 Days |
8 Days |
11 Days |
|
21~50 Pieces |
1~2,000 cm2 |
6 Days |
9 Days |
12 Days |
10 Layer |
1~10 Pieces |
1~2,000 cm2 |
4 Days |
7 Days |
12 Days |
|
11~20 Pieces |
1~2,000 cm2 |
5 Days |
8 Days |
13 Days |
12 Layer |
1~10 Pieces |
1~2,000 cm2 |
4 Days |
8 Days |
14 Days |
|
11~20 Pieces |
1~2,000 cm2 |
5 Days |
9 Days |
15 Days |
Additional lead time could apply as follows:
-
If surface treatments are done with the 3 options: gold plating, immersion gold, and ENTEK (Please allow 1 extra business day).
-
If the drilling holes are more than 5,000 (Please allow 1 extra business day).
-
If orders are place ON HOLD.
-
If payments are in pending status.